|
Installation
These step-by-step instructions will guide you through the basic
installation process for most Keystone™ products. For more detailed
information about specific products or to meet your specific site
situation, consult your local Keystone representative. |
Step One: Prepare the base leveling pad.
Remove all surface vegetation and debris. (Do not use this material as
backfill.) After selecting the location and length of the wall,
excavate the base trench to the designed width and depth.
Start
the leveling pad at the lowest elevation of the wall. Level the
prepared base with 6" of well-compacted granular fill (gravel, road
base, or 1/2"-3/4" [13-20mm] crushed stone). Compact to 95% Standard
Proctor or greater.
Keystone recommends additional
trench depth for below-grade placement of Keystone retaining wall units on a ratio of
1" (25mm) below grade for each 8" (200mm) of wall height above grade
(to a maximum of three units buried). This lowers the base course below
grade, locking the wall in place, and also helps prevent erosion and
scouring at the base of the wall. The base trench should be wide enough
to allow for the Keystone unit and drainage zone.
An
option to a compacted, granular material leveling pad is to use a
non-reinforced concrete leveling pad. In some cases, contractors find
this a time-saving approach. Walls built to a level condition on a
sloping grade require a stepped base. It is best to work out the
stepped base as the wall steps up in elevation. If a concrete leveling
pad is used, the step-up height needs to exactly match the Keystone
unit height. |

|
Step Two: Install the base course.
Place the first course of Keystone units side by side (with sides
touching) on the prepared base, with the paired pin hole facing up.
Make sure each unit is level side to side and front to back. The first
course is critical for accurate and acceptable results. For alignment
of straight walls, use the pins or the straight back edge of the unit;
using the front face will give irregular alignment due to the rough
split texture. For constructing curved walls, use the front pin
position for best results. Minimum radius for convex and concave curves
is 3'6" (1m). |
 |
Step Three: Insert the interlocking fiberglass pins.
Place the reinforced fiberglass pins into the paired holes (2) of each
Keystone unit. (Pins of adjoining units should be 12" [305 mm] on
center.) Once placed, the pins create an automatic setback for the
additional courses. According to wall requirements and design, place
pins in the front holes for near vertical (1/8" [3mm]) setback and the
rear holes for 1 1/4" (32mm) setback per course. |
 |
Step Four: Install and compact backfill and corefill material.
Fill in all voids in and between Keystone units using 1/2"-3/4"
(13-20mm) crushed stone or clean, well-draining granular fill. Place
drain zone behind the units as required to achieve total 2’ (0.6m)
depth of drainage zone from unit face. Pea gravel should not be used.
Compact material in unit cavities appropriately to eliminate settling.
Next,
if economical, use existing soils for backfill behind the gravel
drainage zone. (Heavy clays or organic soils are not recommended due to
water-holding properties.) In some situations, poor site soils will
cause higher reinforcement costs, so economics of using import soils
should be reviewed. Compact soils to a minimum of 95% Standard Proctor
compaction, placing fill in 8" (200mm) lifts on a course-by-course
basis or as specified by a Professional Engineer. (Use only walk-behind
mechanical compaction equipment within 3' [1m] behind the units to
avoid localized overstress.) Sweep off any pebbles or debris so the
next Keystone units rest evenly upon the layer below. |

|
Step Five: Geogrid installation
For taller or more critical walls that require use of geogrid, continue
the installation process with Step 5. If geogrid is not required, skip
to Step 6.
Step 5A.
Excavate reinforced soil area. Remove existing soils in the reinforced
soil area to the maximum embedment length of the geogrid design.
Provide a generally level soil condition behind the wall units for the
placement of each geogrid layer.
Step 5B. Cut
geogrid. Cut sections from geogrid roll to the specified length
(embedment depth). Geogrid roll direction is from the wall toward the
embankment. Check manufacturer’s criteria for biaxial or uniaxial
geogrids. In most cases, correct orientation is to roll the geogrid
perpendicular to the wall face.
Step 5C. Install
geogrid. Hook geogrid over the Keystone fiberglass pins to ensure a
positive mechanical connection between the unit and geogrid.
Step 5D.
Secure geogrid. Pull the pinned geogrid taut to eliminate loose folds.
Stake or secure back edge of geogrid before and during backfill and
compaction. Remove stakes, if desired, once backfill is placed. Place
additional sections of geogrid, abutting each other, for continuous
coverage at each layer.
Step 5E. Install next course of Keystone units.
Step 5F.
Place compacted backfill over geogrid in 8" lifts. Provide a minimum of
6" (150mm) reinforced fill coverage prior to driving equipment over the
geogrid with tired equipment. Avoid driving or turning vehicles
directly on geogrid to avoid excessive damage. |

|
Step Six: Install additional courses.
Place the next course of Keystone units over the fiberglass pins,
fitting the pins into the kidney-shaped recesses. Center the unit over
the two underlying units as shown. Visually sight down in the
kidney-shaped recess for pin positioning. Pull the Keystone unit toward
the face of the wall until it makes full contact with |
|
|
|
|